Columbia and nearby residents divided over disputed transmission line plan

Columbia City Council holds a public hearing on a proposed $35M, 161-kilovolt transmission line linking two substations, drawing concerns from residents over safety and property values.

The Columbia City Council is scheduled to conduct a public hearing during Monday’s meeting regarding a proposal to install a 161-kilovolt transmission line along the city’s south and southwest corridors.

The proposed line would establish a connection between the Perche Creek and Grindstone substations, with the designated route passing along Scott Boulevard, Vawter School Road, Nifong Boulevard, and Grindstone Parkway.

While proponents argue that the project would contribute to the development of more dependable infrastructure throughout Columbia, a number of residents contend that it presents a potential hazard to those living nearby, as well as a negative impact on surrounding property values.

Jason West, a spokesperson for the Columbia Utilities Department, stated that the project would serve to strengthen the reliability of the electric grid.

“Right now, we have high-voltage transmission lines coming into the city, but there’s not very many paths for those to continue through the city,” he said.

Columbia Water and Light is set to present the proposed designs to the council at Monday’s public hearing. Although the electrical transmission line project was originally introduced in 2009, it has since been brought back under consideration.

The water and light board voted in February to proceed with the selected route, choosing it over a shorter yet considerably more costly alternative.

“I think there’s been enough turnover in administration, both at the city level and the council level, that there were enough people that recognized the need for this project and wanted to make sure it didn’t totally go away,” West said.

The estimated cost of the project stands at approximately $35 million; however, significant opposition has emerged among local residents. Sarah Nelson, a mother of two children who attend Mill Creek Elementary School on Nifong Boulevard, noted that the proposed route would pass within 100 to 300 feet of two elementary schools.

“We should be surrounding our schools with trees, green spaces and natural beauty , not towering steel transmission structures,” Nelson said.

Even if the project receives approval from the city, construction could take close to a decade to reach completion.

“Just the approval process, getting the final site design and getting it approved could take five to seven years before we can even start the construction process,” West said.

Mayor Barbara Buffaloe indicated in a Facebook video that she anticipates a significant turnout for the long-debated project at the council’s meeting, which is scheduled to commence at 7 p.m.