The Missouri Department of Transportation (MoDOT) is fully prepared to address the potential of winter weather conditions coinciding with the Thanksgiving holiday, despite an anticipated surge in traffic volume across the state.
The KOMU 8 First Alert Weather team has issued a First Alert Weather Day for Thanksgiving Day, Thursday, in response to a developing storm system that is expected to bring a mix of rain and snow to the region. The system carries the potential to create notable travel disruptions, particularly across eastern portions of Missouri.
Eric Kopinski, MoDOT’s Improve I-70 Statewide Program Director, stated that the department has been working in close coordination with law enforcement agencies, municipalities throughout the state, and the Missouri State Emergency Management Agency to ensure public safety during the holiday period.
“Our crews are experienced and they are going to be ready for it,” Kopinski said. “We are going to be prepared and keep I-70 as free flow as possible.”
Kopinski confirmed that additional traffic engineers will be deployed and working in close coordination with MoDOT to continuously monitor weather conditions throughout the holiday. He further noted that the department is tracking developing weather patterns with the same level of vigilance as the general public.
“There’s a lot of traffic that is going to be happening,” Kopinski said. “The unknown is what happens when the snow comes, how bad is it and how much notification do we get?”
MoDOT maintains an established plowing priority system, which designates the order in which roadways are cleared during snowfall events. Kopinski strongly advised motorists to avoid traveling unless absolutely necessary and to adjust their travel plans accordingly, particularly given the presence of active construction zones along I-70.
Although construction activity is scheduled to be suspended from Wednesday afternoon through Monday morning, approximately 65 miles of active construction zones remain present along I-70 throughout the state. Speed limits in several of these areas have been reduced from the standard 70 mph to 55 mph, owing to narrowed lanes, concrete barriers, and the absence of road shoulders.
“We set our speed limit based on design criteria and what it takes to drive through that work area safely,” Kopinski said.