Airport authority moves to automate exit process from secured zone to baggage claim

Columbia Regional Airport will install $700K automated exit lanes with breach control technology, replacing TSA-monitored doors and saving the cost of hiring 3-4 new staff.

Columbia Regional Airport is preparing to implement a significant change to the way passengers transition from the secure gate area to the public terminal.

The airport, known by its designation COU, intends to install automated exit lanes equipped with breach control technology. This upgrade will replace the existing double-door configuration, which currently requires the physical presence of a Transportation Security Administration (TSA) agent for monitoring purposes.

Mike Parks, the airport’s longstanding manager and director of Columbia’s newly established Airport Department, disclosed that TSA informed the airport earlier this year of its intention to withdraw staff from the exit lane monitoring role.

The forthcoming automated system will operate continuously, 24 hours a day, and will feature two distinct exit lanes in place of the single, wider exit area currently in use. The system will incorporate sensors and alarm mechanisms designed to detect any unauthorized attempts to access the secure area or introduce prohibited items.

“It will ensure that our customers are secure where they’re at, ensure that we’re in compliance at all times, and that’s ultimately what the goal is with this project,” Parks said.

Parks further noted that, under the existing setup, the airport would have been required to hire between three and four additional full-time employees to fulfill the exit lane monitoring responsibilities.

“It’s definitely going to save the airport money over time,” he said.

COU anticipates having the new exit lanes fully operational by the following spring. Parks estimated the construction cost at over $600,000, with supplementary expenses bringing the overall total to upward of $700,000.

The Columbia City Council formally approved several measures to advance the project during its meeting on Monday. According to council documentation pertaining to the initiative, the construction phase is projected to span approximately 150 days.

The installation of the new exit lanes represents one of several major development projects currently in planning or underway at COU. These include upgrades to the north parking lot and the addition of a full-production kitchen, all taking place during a period of continued growth in flight offerings at the airport. Allegiant Air is also set to launch its new route to St. Pete-Clearwater International Airport on Thursday.